Bitzer delivers cooling for Sochi Winter Games

Bitzer, Sochi, winter Olympic games, compressor, air conditioning
The refrigeration and air-conditioning requirements of five stadiums at the Sochi Winter Olympic Games were met using Bitzer screw compressors.

Bitzer screw compressors played a key role in the refrigeration and air-conditioning systems delivered by Finnish manufacturer Suomen Tekojää Oy for five stadiums of the Olympic Winter Games at Sochi. Established in 1997, the company has built refrigeration systems for over a hundred ice rinks in Russia and around 500 worldwide.

The projects were as follows

• Shayba Arena: four CSH (ice surface) and six CSH compressors (air conditioning). ‘Shayba’ is the Russian word for the puck used in ice hockey.

• Ice-hockey training stadium: four CSH (ice surface) and two CSH compressors (air conditioning).

• Figure-skating training stadium: four CSH (ice surface) and two CSH compressors (air conditioning).

• Curling arena: three HSK (ice surface), three HSK (air conditioning) and three HSK compressors for either function.

• Bobsleigh training stadium: four CSH (ice surface).

To ensure that everything ran to plan, a back-up system was installed for each refrigeration system.

For more information on this story, click here: April 2014, 133
Related links:
Related articles:



modbs tv logo

Lighting the way

Halesowen College has set a sustainability example for higher education institutions by installing smart lighting as part of its latest environmental initiative, making up to 85% energy savings compared to the previous system.

BESA updates HIU Test Standard

The Building Engineering Services Association (BESA) has announced an important update to its UK Heat Interface Unit (HIU) Test Standard, further strengthening performance benchmarks and supporting the sector’s readiness for incoming heat network regulation.