G&H installs biomass boiler

A biomass boiler has been installed at Harrogate Grammar School as part of a project to modernise its heating and hot-water systems. The project involved G&H Sustainability completely stripping out the existing plant room and stripping out old gas-fired boilers , water heaters, pumps and pipework.

The old equipment was replaced with a fully automated 199 kW biomass boiler from Hoval and a building-management system for complete control.

Andrew Hudson, a director of G&H Sustainability, said, ‘We prefabricated the majority of the pipework within the plant room due to the time constraints of the project. This worked well because we were able to complete the on-site installation works in a much shorter time frame’

For more information on this story, click here: April 2015, 104
Related links:
Related articles:



modbs tv logo

Industry leaders gather at CIBSE’s Measuring Performance and Facilities Management conference

CIBSE’s Measuring Performance and Facilities Management conference recently brought together leading voices from across the built environment
to explore the evolving landscape of building performance and operational excellence.

Independent testing crucial to bridge retrofit confidence gap, BSRIA study reveals

New research from the Building Services Research and Intelligence Association (BSRIA) highlights a significant confidence gap between construction professionals and the general public regarding the effectiveness of building retrofits.