Power Electrics completes challenging standby-generator installation

Power Electrics
Power Electrics worked with Evans Electrical to install this 1250 kVA standby generator at Centrica’s offices in Cardiff.

Power Electrics has installed a 1250 kVA standby generator in the basement car park of Centrica in Cardiff by digging a pit to provide the required headroom. The company worked closely with electrical contractor Evans Electrical to install this diesel generator, control system and bulk fuel tank.

The work included the construction of a plant room to reduce noise levels to 65 dB(A) at 1 m and a flue extension to clear the roof of the eighth floor of the building.

Nik Mason, director of Evans Electrical, commented, ‘This was a particularly demanding application, and it was completed on time and within budget thanks to Power Electrics’ expertise and their ability to successfully co-ordinate all the trades on site.’

For more information on this story, click here: Aug 09, 130
Related links:
Related articles:



modbs tv logo

Finalists announced for the 2025 Pump Industry Awards

The Pump Industry Awards has revealed its highly anticipated finalists for 2025, showcasing the very best in innovation, performance and contribution across the pump sector. The winners will be celebrated at the prestigious gala dinner on Thursday 13th March at the Hilton Hotel, St. Georges Park in Burton on Trent.

Electrical businesses brace for project delays in 2025

The latest quarterly Building Engineering Business Survey (BEBS) has revealed that close to two thirds (63%) of electrotechnical and engineering services businesses are worried about delays to projects and the impact this can have on cashflow.